Update on 227 Berkeley

July 19, 2019


At 227 Berkley place, Trim phase I was completed along with priming of all walls/ceiling and tiling on all the units. Hardwood flooring install has also started on the job and kitchens and vanities cabinets are estimated to be ready by first week of August.

 

June 18, 2019


Tile and phase I of trim have started and are estimated to be done before July 15th. Once those are complete we could start priming the walls and ceiling.

227 Berkley Pl June19-01.jpeg

The property will now be finishing with :

  • Wolf/Subzero appliance package

  • Custom Italian cabinetry with quartz countertops and full quartz kitchen backsplash

  • Engineered hardwood flooring throughout

  • Full height marble tile in the in master baths

  • Large format porcelain tile in the secondary baths

  • Kohler plumbing fixtures

  • Sierra Pacific windows

  • Complete façade restoration

 

May, 13, 2019


227 Berkley Pl April 19-06.jpeg

Work has been going in a good pace and ahead of schedule. On the exterior, we are looking to start installing the roofing by end of next week. While on the interior we started sheet rocking the building last week 

 

May 2, 2019


Rough HVAC and Rough Plumbing are officially complete at 227 Berkeley Place!

 

March 19, 2019


Screen Shot 2019-03-19 at 1.02.48 PM.png

Interior framing and bulkhead framing is officially complete at 227 Berkeley Place!

January 22, 2019


We picked up full building permits for 227 Berkeley Place and expect to start interior framing phase 1 soon!

unnamed.jpg

January 4, 2019


The interior structural work is officially underway!

December 16, 2018


227 Berkley Aug18-03.jpeg

More information coming soon.