Update on 423 3rd St

July 18, 2019


At 423 3rd St, kitchens and vanity countertops were all installed.  Final MEP inspections and permit close outs are beginning in August for CO.

 

June 22, 2019


Kitchen cabinets and vanities were recently installed.th.  Countertops were templated on the 10th, and are scheduled to be installed soon

Plumber will be starting final plumbing as soon as counter tops are installed.  All appliances and final plumbing fixtures were delivered and are ready to be installed. Once installed then final paint will start and is estimated to be completed by mid-July.

423 3rd Sr June19-03.jpeg
 

May 2, 2019


Screen Shot 2019-05-03 at 4.27.09 PM.png

We’re officially on Phase II of Finishing at 423 3rd Street!  

Sheetrock taping finished mid-March and painting was started immediately thereafter.

 

March 19, 2019


Sheetrock is 100% complete at 423 3rd Street! 

 

January 22, 2019


Insulation and fire stopping is 100% complete at 423 3rd Street!  Sheetrock is currently underway. We expect to be 100% completed with sheetrock in the next week.

unnamed.jpg

January 4, 2019


Paint and interior trim are in progress at 423 3rd Street!

unnamed-2.jpg
unnamed-1.jpg

December 16, 2018


Insulation and sheetrock are in progress at 423 3rd Street! 

unnamed-1.jpg
BrooklynMagan Carrigan