Update on 377 DeGraw

July 18, 2019


377 Degraw st July19-01.jpeg

At 377 Degraw St. we are building the extension walls and demolition of rear wall is completed.  Framing on the extension is now on going. 

 

June 21, 2019


377 Degraw st June19-03.jpg

This week we will install the I-Beams for the Fire Escape, once finished the facade framing can start. HVAC and plumbing subcontractors will be back to finish their rough scope of work  They are currently at 75% completion and estimated to be completed by mid-July.  Upon completion the Rough Electric & Sprinklers will start.

 

May 13, 2019


377 Degraw April 19-03.jpeg

Con Ed is bringing in new service and the new roof will go on immediately after the addition is complete.

377 Degraw April 19-01.jpg
 

May 2, 2019


Screen Shot 2019-05-03 at 4.21.43 PM.png

Interior framing Phase-1 is 100% complete at 377 DeGraw Street!

 

March 19, 2019


The extension slab at 377 DeGraw Street has been poured and the structural steel framing is complete.

January 4, 2018


Work is progressing nicely at 377 DeGraw Street!

The concrete block installation, aka Concrete Masonry Unit (or “CMU”) installation, started on the rear extension wall. Furthermore, the interior light-gauge framing began.

unnamed-1.jpg
unnamed-3.jpg

December 18, 2018


Structural reinforcement of the existing joists is completed at 377 DeGraw Street! 

unnamed.jpg
BrooklynMagan Carrigan