Update on 116 Reed St (Reed Estates)

December 11, 2018


116 Reed St Nov2018-01.jpg

Reed Estates officially has all 26 units set and the first phase of units are scheduled to be completed and appraised the first week of January right in time for prime renting season.

Unit 15 has final plumbing in progress. 

Units 9 to 14 tile is in progress. From those units, Unit 13 will be the first unit to go to Final Plumbing the week of 11/19.

Trim is in progress at Units 6 to 8. 

Units 5, 16, & 17 are in sheetrock. 

Rough mechanicals in Units 18 to 22 are being completed. City Rough Framing Inspections estimated to begin 11/16. 

We are also estimated to start rough mechanicals in Units 23-26 the week of 11/26.

Final framing punch outs are being completed now in units 1, 2, & 3.  Façade install and underground utilities are scheduled to start 11/26.

PhiladelphiaMatthew Callahan