Update on 1 Elden Dr (Saddle River Homes)

September 1, 2019


 At 1 Elden Drive, Saddle River, NJ construction is finishing up at the property and the sellout process has officially started. The property listing can be viewed by clicking the following link below:

 

August 8, 2019


Construction is moving along very nicely at 1 Elden Drive Saddle River.

We are nearly finished with the home and the sellout process has started.

 

July 18, 2019


The interior doors have been installed along with the closet shelving.  The ceramic tile has just begun installation.  The radiant heating has been installed in the flooring. The basement has been inspected and insulation will begin this week. The bluestone rear porches are complete.   The Belgium block curbing has been completed. 

 

June 26, 2019


Great progress at 1 Elden Drive: The interior has been insulated and drywalled installed and spackled.  A prime coat of paint has been completed.  The hardwood floor has been delivered and being installed.   The exterior stone work is 75% complete.  

 

June 19, 2019


Screen Shot 2019-06-24 at 3.10.01 PM.png
Screen Shot 2019-06-24 at 3.10.13 PM.png

Façade has been completely installed.  In the inside of the house the sheetrock is 70% completed, the rough electric is 70% done and approximately 25% of the switches and outlets are in place.  The CO should be around September 15.

 

June 10, 2019


 

May 13, 2019


1 Elden Drive is progressing nicely. The basement and garage floors have been completed.  The basement has been framed and mechanical roughing started. The interior stairs have been installed.  On the exterior the cedar shake siding is almost complete.  

ED64.jpg
 

February 26, 2019


Rough Plumbing, Electric and HVAC Mechanical is 90% complete at this time.

 

December 7, 2018


The project site has been stumped and the stumps have been removed. The topsoil has been stockpiled and soil erosion controls installed. 

Excavation for the foundation has been complete and ready for footing formwork, scheduled for tomorrow. 

The builder has encountered 4 existing seepage pits and one septic tank in the foundation area that were not shown on the drawings. The septic tank was pumped out and all of the tanks were crushed and filled with gravel. 

There are no major issues at this time to delay the project.

Demolition has been completed and inspected by Saddle River.

The building department is awaiting one more signature before release of construction permit. 

The contracts have been released for excavation through wood framing. 

DMR is expecting to start construction in the next couple weeks.