Update on 4901 Bergenline Ave (The Station)

July 18, 2019


Work is progressing nicely on Bergenline Station.  The beginning excavations and underpinning of all outer walls below ground is completing along the front and side elevations.   

image003.jpg
image005.jpg
image006.jpg
 

June 28, 2019


‘Phase 1 Demolition’ scope of work throughout the building’s basement and 1st floor has been substantially completed.

Screen Shot 2019-07-05 at 12.56.59 PM.png
 

May 17, 2019


Progress on The Station going smoothly with basement demo finishing up and excavation for underpinning started.

IMG_0140_1558010194064.jpg
 

May 13, 2019


  • Phase 1 Interior Demolition approx. 60% complete

  • First floor all debris removed, walls removed to brick, all partition walls and non-structural ceiling elements removed

  • Basement partition walls and non-structural walls being demolished, piping and utility conduit being removed

 

December 3, 2018


unnamed-1.jpg

The design team is in process of redesigning the foundation plan to leave the first floor elevations as requested by building department.

The demolition contractor has already been contracted in preparation for work.

Asbestos removal is to begin around 10/15/2018 and will take estimated 3 weeks to complete.

Subject to approval, demolition will then begin with an estimated duration of about 2-3 months at which time the City is expected to be ready for review and approval.

Upon subject to receiving full building permits, construction will then proceed with an estimated construction timeline of about 22 months.

unnamed.jpg
New JerseyMagan Carrigan