Update on 8 Kenwood (Saddle River Homes)

February 26, 2019


The asphalt roof has been completed on the new building and on the pool room. 

 

December 11, 2018


The house has been demolished and the site cleared of debris. 

The plans have been revised to allow for a higher basement to 9’ from the existing 7’-6”.

The builder has started the excavation for the footings at this time.

There are no major issues at this time to delay the project.

The architect has been in consultation with the building inspector on options for this project.

The engineer has completed a plan for the building inspector to review to get past this regulation.

If this is not acceptable a residential fire sprinkler system will need to be installed.

New JerseyMagan Carrigan