Update on 1070 Bergen St

July 19, 2019


 At 1070 Bergen St, the rear extension walls are built.  Once façade framing is completed zip wall will be installed and interior framing of the extension will start.

 

June 18, 2019


1070 Bergen St June19-01.jpg

The building of the rear extension, CMU walls is ongoing and we are at the 2nd floor deck.  The project is  at 75% completion and estimated to be completed by mid-July.  At that time the  Rough Electric & Sprinklers will start.

This four condominium building is in high demand!

 

May 13, 2019


1070 Bergen April 19-01.jpeg

The Interior framing is moving nicely and we still are on track to finish in early May!

1070 Bergen April 19-02.jpeg
 

May 2, 2019


All Footings have been poured and the foundation is complete at 1070 Bergen Street!

 

March 19, 2019


Screen Shot 2019-03-19 at 1.44.23 PM.png
Screen Shot 2019-03-19 at 1.44.11 PM.png

Interior framing is about 50% complete at 1070 Bergen Street! It’s estimated to finish soon!

January 3, 2019


The interior light-gauge framing is underway at 1070 Bergen Street!

unnamed.jpg

December 3, 2018


unnamed.jpg

Structural reinforcement of the existing joists is completed at 1070 Bergen Street!

We are now digging the extension footings and will start placing rebar in the footings next week for the rear property extension.