Units 6-8 are not 100% framed and site plumbing is expected to be completed by the end of the week. 

2031 Lombard Mar2019-01.JPG
 

December 9, 2018


Moderna is near complete with foundations. 

Before the builder can start framing they must install the garage slab steel and structure steel and also bring in all the water and sewer due to the extremely tight confines. 

They are also very close to coming to market.

We have received inspection reports documenting the completion of the remaining 60% of Foundation and 100% of the Backfill & rough Grade at 2031 Lombard Units #1 and #2. 2031 Lombard Partners LLC

The project is moving steadily forward and values in Rittenhouse Square continue to escalate as virtually no other 100% new construction Town Home properties are being built there.