Update on 285 7th St

July 19, 2019


The permit for 285 7th St was picked up June 27th.  Our subcontractors start date on the job will be August 1st.  

 

June 18, 2019


We received the permit approval on April 19th for 285 7th Street job.    Once we have the fence permit we will attempt to pick up the building permit soon after.

 

May 2, 2019


We finished our pre-filing sprinkler application and have it fully submitted for review.

 

March 19, 2019


Screen Shot 2019-03-19 at 12.43.38 PM.png

Final approvals coming soon!