Update on 302 Poplar St (Liberty Park Place)

September 15, 2019


The basin is finished.  The units will be set five units at time and take an estimated five weeks per unit group. Completion to set all units is estimated at sixteen weeks to set all town homes.  Podium Steel will be installed after setting the townhomes

 

June 9, 2019


We broke ground several weeks ago on this 13 Unit Town Home and Mixed Use Development including retail, 20 rental apartments  and 13 Town Homes.  

1.png
 

May 13, 2019


All 13 foundations for the homes are complete.  The builder is now installing the footings for the commercial building.

302 Poplar Apr2019-01.jpg
302 Poplar Apr2019-04.jpg
 

March 21, 2019


All foundations are not officially complete and the builder will finish pouring the slabs this week. 

302 Poplar Mar2019-04.jpg