Update on 44-50 N 3rd St (Lippincott Alley)

May 13, 2019


Lippincott Alley is reaching the critical finishing stages and is on track to pave the asphalt driveway and paver walkway by the end of May - which is a major milestone for the marketing of the properties. 

44 N 3rd Apr2019-03.jpg
 

March 21, 2019


Lippincott Alley is underway on many phases now and is nearing finishing for this spring!

44 N 3rd Mar2019-01.JPG
 

January 2019


This week Units 7, 8, and 9 will begin tile.

Units 5 and 6 will start trim.

Units 1, 3 and 4 are finishing drywall. 

Unit 2 will begin drywall.

Unit 10 continues with framing punch lists while it is on hold for neighbor access and metal install on its west façade. Access resumes Jan 16.

Units 7 & 8 are being prepped for sale and will be completed this quarter.

44 N 3rd Jan2019-02.jpg
 

DECEMBER 2018


Scaffolding is up on the west neighbor’s property, and brick on the west wall of unit 10 is expected to finish by the end of the week.

44 N 3rd Dec2018-02.jpg